Glisson OS Rollout Roadmap

Prepared for Glisson Camp & Retreat Center · October 2026 – March 2027

Kickoff
Oct 2026
CircuiTree data copy begins; Retreats build starts
Retreats live
Early Nov
Fallback: Dec build → early Jan launch
Camp cutover
Jan 2027
Protected date — does not move
Phase 3 features
Nov – Mar
One to two features live at a time
Rollout timeline

Retreats first, Camp cutover protected, features layered in behind it

The gold line marks the Camp & CircuiTree cutover — the one date in this plan that holds even if Retreats slips. Dashed amber segments are the workstreams built to flex if that happens.

PROTECTED CUTOVER Oct ’26 Nov ’26 Dec ’26 Jan ’27 Feb ’27 Mar ’27 Retreats — Primary Plan Retreats — If Delayed Camp & CircuiTree Migration Financial Suite Safety & Compliance Forms Donor CRM Email Marketing QR Code Generator Facilities & Site Ops Training & Feedback John McGreevy Contingency only Shelnutt · Gaines Lloyd · Rhinehart Will Rhinehart Sarah Shelnutt C. Russell Davis Cameron Jones Cameron Jones Blake Corbin Monthly, per active phase Build Launch (early Nov) Build (if delayed) Launch early Jan Data Copy Parallel Run (CircuiTree + OS) Cutover Push Go-Live Financial Suite Migration Medical Forms · BG Checks · Waivers Ready Donor CRM Build flexes if needed Email Marketing Build flexes if needed QR Codes Basic (Retreats) Facilities
Confirmed — primary workstream
Confirmed — secondary priority
Prep / parallel-run sub-stage
Contingency — flexes if triggered
Go-live / readiness milestone
Protected date — does not move
Reflects the working plan as of September 2026: Retreats targets an early-November launch with a December–January fallback; the Camp & CircuiTree cutover in January is held fixed regardless; Donor CRM and Email Marketing are the workstreams built to absorb schedule pressure if the Retreats fallback triggers.
Contingency plan

If November retreats slip

What moves, and what doesn't

Retreats falls back to a December build with an early-January launch instead of early November.

Camp & CircuiTree cutover holds its January date. This is the highest-value module and the one your broader rollout playbook depends on proving out first — it does not move to absorb the delay.

Donor CRM and Email Marketing are the workstreams that flex instead, sliding into February–March if the team's time is needed to protect the Retreats fallback and the Camp cutover in the same window.

Team & ownership

Who's driving each part of the rollout

Every workstream on the timeline above has a named owner on both sides — the pill shows which part of the roadmap they're tied to.

STATION16 team

Joel Roberts
Lead Development & Implementation Architect
All phases
David Gordon
Content, Data Management & Features Architect
All phases
Jessi Biagioni
Design & Implementation Support
All phases
Cara Baxter
Project Management, Communications
Training cadence
Brenton Smith
Design & Implementation Support
All phases

Glisson team

Will Rhinehart
Business Manager — key point person
Financial Suite · Camp Migration
John McGreevy
Director of Retreats
Retreats
Sarah Shelnutt
Summer Camp Registrar
Camp migration
Stephanie Gaines Lloyd
Director of Summer Camps
Camp oversight
C. Russell Davis
Executive Director
Donor CRM
Cameron Jones
Dir. of Communications & Program Advancement
Email & QR, supports CRM
Blake Corbin
Director of Facilities
Facilities
Full staff directory: glisson.org/team
Decisions log

What's confirmed so far

Contract

Glisson has no CircuiTree renewal notice window to work around.

Confirmed directly by Glisson — removes the one hard external deadline from the plan.

Priority

If Retreats slips, the Camp & CircuiTree cutover date is protected; Donor CRM and Email Marketing absorb the schedule pressure instead.

Camp is the highest-value module and the one the broader rollout playbook depends on proving out first.

Scope

Medical Forms, Background Checks, and Digital Waivers/E-signatures are elevated ahead of Donor CRM and Email Marketing, targeted to be ready before the Camp cutover.

These are registration safety & compliance essentials, not optional add-ons.

Training

Monthly walkthrough and training per active phase, doubling as a feedback loop into continued development.

Confirmed: any month where more than one phase is live splits into separate per-module sessions rather than one combined session.

Scope

A small, functional slice of Facilities & Site Operations moves up to November, sized to support Retreats.

Retreats needs basic facility/space management to launch; the full Facilities & Site Ops build stays targeted for March.